Skip to main content

General Question about Surveying and Levelling Part 2

 

This image has an empty alt attribute; its file name is levelling-instrument-2-258549518.png

Question No. 41
Which of the following statements is incorrect?
(A) Error due to refraction may not be completely eliminated by reciprocal levelling
(B) Tilting levels are commonly used for precision work
(C) The last reading of levelling is always a foresight
(D) All of the above statements are incorrect
Answer: Option D
Question No. 42
In levelling operation,
(A) The first sight on any change point is a back sight
(B) The second sight on any change point is a fore sight
(C) The line commences with a fore sight and closes with a back sight
(D) The line commences with a back sight and closes with a foresight
Answer: Option D
Question No. 43
The length of a traverse leg may be obtained by multiplying the latitude and
(A) Secant of its reduced bearing
(B) Sine of its reduced bearing
(C) Cosine of its reduced bearing
(D) Tangent of its reduced bearing
Answer: Option A
Question No. 44
While working on a plane table, the correct rule is:
(A) Draw continuous lines from all instrument stations
(B) Draw short rays sufficient to contain the points sought
(C) Intersection should be obtained by actually drawing second rays
(D) Take maximum number of sights as possible from each station to distant objects
Answer: Option B
Question No. 45
The vertical angle between longitudinal axis of a freely suspended magnetic needle and a
horizontal line at its pivot, is known
(A) Declination
(B) Azimuth
(C) Dip
(D) Bearing
Answer: Option C

Question No. 46
In the cross-section method of indirect contouring, the spacing of cross-sections depends upon
(i) Contour interval
(ii) Scale of plan
(iii) Characteristics of ground
The correct answer is
(A) Only (i)
(B) (i) and (ii)
(C) (ii) and (iii)
(D) (i), (ii) and (iii)
Answer: Option D
Question No. 47
Transition curves are introduced at either end of a circular curve, to obtain
(A) Gradually decrease of curvature from zero at the tangent point to the specified quantity at
the junction of the transition curve with main curve
(B) Gradual increase of super-elevation from zero at the tangent point to the specified amount
at the junction of the transition curve with main curve
(C) Gradual change of gradient from zero at the tangent point to the specified amount at the
junction of the transition curve with main curve
(D) None of these
Answer: Option B
Question No. 48
A and B
sextant. The correct horizontal angle is
(A) cos - (B) cos - (C) cos - (D) None of these
Answer: Option A
Question No. 49
Tilt of the staff in stadia tacheometry increases the intercept if it is
(A) Away from the telescope pointing down hill
(B) Towards the telescope pointing up-hill
(C) Away from the telescope pointing up-hill
(D) None of these
Answer: Option C
Question No. 50
Three point problem can be solved by
(A) Tracing paper method
(B)
(C)

(D) all of the above
Answer: Option D
Question No. 51
A dumpy level is set up with its eye-piece vertically over a peg . The height from the top of
peg to the centre of the eye-piece is 1.540 m and the reading on peg is 0.705 m. The level is
then setup over . The height of the eye-piece above peg is 1.490 m and a reading on is
2.195 m. The difference in level between and is
(A) 2.900 m
(B) 3.030 m
(C) 0.770 m
(D) 0.785 m
Answer: Option C
Question No. 52
In a lemniscate curve the ratio of the angle between the tangent at the end of the polar ray and
the straight, and the angle between the polar ray and the straight, is
(A) 2
(B) 3
(C) 4/3
(D) 3/2
Answer: Option D
Question No. 53
The bellow figure is a conventional sign of
(A) Mosque
(B) Temple
(C) Church
(D) Idgah
Answer: Option D
Question No. 54
A level when set up 25 m from peg A and 50 m from peg B reads 2.847 on a staff held on A and
3.462 on a staff held on B, keeping bubble at its centre while reading. If the reduced levels
of A and B are 283.665 m and 284.295 m respectively, the collimation error per 100 m is
(A) 0.015 m
(B) 0.030 m
(C) 0.045 m
(D) 0.060 m
Answer: Option D

Question No. 55
Hydrographic surveys deal with the mapping of
(A) Large water bodies
(B) Heavenly bodies
(C) Mountainous region
(D) Canal system
Answer: Option A
Question No. 56
Bowditch rule is applied to
(A) An open traverse for graphical adjustment
(B) A closed traverse for adjustment of closing error
(C) Determine the effect of local attraction
(D) None of the above
Answer: Option B
Question No. 57
Angles to a given pivot station observed from a number of traverse stations when plotted, the
lines to the pivot station intersect at a common point
(A) Angular measurements are correct and not the linear measurements
(B) Linear measurements are correct and not the angular measurements
(C) Angular and linear measurements are correct and not the plotting of traverse
(D) Angular and linear measurements and also plotting of the traverse are correct
Answer: Option D
Question No. 58
Pick up the correct statement from the following:
(A) The horizontal angle between magnetic meridian and true meridian at a place is
called magnetic declination or variance of the compass
(B) The imaginary lines which pass through points at which the magnetic declinations are equal
at a given time are called isogonic lines
(C) The isogonic lines through places at which the declination is zero are termedagonic lines
(D) All the above
Answer: Option D
Question No. 59
Straight, parallel and widely spaced contours represent
(A) A steep surface
(B) A flat surface
(C) An inclined plane surface
(D) Curved surface
Answer: Option C
Question No. 60
The real image of an object formed by the objective must lie

(A) In the plane of cross hairs
(B) At the centre of the telescope
(C) At the optical centre of the eye-piece
(D) Anywhere inside the telescope
Answer: Option A
Question No. 61
For a tachometer the additive and multiplying constants are respectively
(A) 0 and 100
(B) 100 and 0
(C) 0 and 0
(D) 100 and 100
Answer: Option A
Question No. 62
Correct distance obtained by an erroneous chain is:
(A) (Erroneous chain length/Correct chain length) × Observed distance
(B) (Correct chain length/Erroneous chain length) × Observed distance
(C) (Correct chain length/Observed distance) × Erroneous chain length
(D) None of these
Answer: Option A
Question No. 63
An imaginary line lying throughout on the surface of the earth and preserving a constant
inclination to the horizontal, is called
(A) Contour line
(B) Contour gradient
(C) Level line
(D) Line of gentle scope
Answer: Option B
Question No. 64
The constant vertical distance between two adjacent contours, is called
(A) Horizontal interval
(B) Horizontal equivalent
(C) Vertical equivalent
(D) Contour interval
Answer: Option D



Comments

Popular post

What is Slump Test of Concrete-Cone Test Procedure | Workability of Concrete

Slump Test of Concrete-Cone Test Procedure | Workability of Concrete Slump test procedure is to determine the workability of concrete. One of the major problems that you had faced in your field work is concrete compaction during mixing.After mix design, you may have doubt, is this design will be ok? Yes, your design willl be ok in terms of strenght point of view of concrete.But the main problem arises when the mixing of fresh concrete, the compaction of fresh concrete will be very tough.In this situation, you can add some plasticizers without affecting your water-cement ratio or cement-aggregate ratio. Before adding plasticizers or superplasticizers to your fresh concrete, you need to check the workability of your concrete.The slump test is used for checking the workability of concrete.Let us check how can we do slump test of fresh concrete. Apparatus used for cone test procedure 1)Measuring scale 2)Tamping rod 3)Base plate 4)Nonporous base plate 5)Mould for slump test.

Different methods of road construction in civil engineering

Different methods of road construction in civil engineering 1) Concrete: It is a common option for road construction purposes as they are a solid material and can be used for building walls and local roads. This method is considerably less prone to wear and tear defects like rutting, cracking, stripping loss of texture, and potholes. This is the main reason for its wide usage. 2) Asphalt: This method of construction replacing concrete method in these days. They are very durable, water-resistant and can go more longer then the concrete. The major advantage of asphalt over concrete is its price. Concrete is very expensive as compared to asphalt. Moreover, asphalt includes low noise during pavement and it is easy to handle it for repairing and maintenance. That is why it is widely accepted and used by the people for the purpose of pavement surfacing. 3) Composite: This method is widely used for the maintenance, recycling, and rehabilitation of the roads. The composite mater

Design Requirement of reinforced Concentrate slab

Table  Content 1 Effective span for concentrate slab design 2 Limiting stiffness 3 Minimum reinforcement 4 Maximum diameter of bar 5 Distribution reinforcement concentrate for slab design 6 Cover to reinforcement Let discuss briefly '''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''' 1. Effective Span for concrete slab design For simply supported slab Minimum of clear span plus effective depth of slab Center to center

What’s the difference between m20 and c20 grade concrete?

 A concrete of Grade C20 means that the concrete will have a compression resistance of 20 N/mm² per square millimeter in 28 days. Proportion for grade C20. C20 is 1:2:4 (1 part cement, 2 parts fine aggregate, and 4 parts coarse aggregate.) where as C20 symbolizes a Cylindrical sample in which cement, fine aggregates, coarse aggregates are mixed in such a ratio that its characteristic compressive strength is 20 N/mm² after 28 days of curing. Fig:- Concrete specimen for testing Generally Strength of Cylinder sample= 0.8 x Strength of Cube. example:- M20 is equivalent to C25 M20 means the grade of concrete is defined as the minimum strength of concrete after 28 days. For the M20 Grade of concrete, The letter ‘M’ refers to the mix, and 20 represents the characteristic strength of concrete in MPa or N/mm². The specified characteristic strength of concrete is determined for 150mm size cube at 28 days. The Characteristic Compressive strength of concrete is defined as the strength of concrete

WHAT ARE THE DESIGN PROCEDURES FOR A BUILDING FOUNDATION?

  DESIGN PROCEDURES FOR A BUILDING FOUNDATION 1. DECIDE THE LOCATION OF COLUMNS & FOUNDATION AND TYPE OF LOADS ACTING ON THEM.(E.X DEAL LOAD,  LIVE LOAD OR WIND LOAD) 2. ESTIMATE ALLOWABLE BEARING PRESSURE OF SOIL USING GROUND INVESTIGATION REPORT. 3. DECIDE DEPTH OF FOUNDATION 4. CALCULATE FOUNDATION AREA 5. DETERMINE VARIATION IN VERTICAL STRESSES 6. CALCULATE SETTLEMENT 7. COST CONTROL 8. CONSIDER TIME 9. VARIATION IN GROUND CONDITION 1. DECIDE THE LOCATION OF COLUMNS & FOUNDATION AND TYPE OF LOADS ACTING ON THEM.(E.X DEAL LOAD,  LIVE LOAD OR WIND LOAD) On the building plan, the position of columns and load bearing walls should be marked, and any other induced loading and bending moments. The loads should be classified into dead, imposed and wind loading, giving the appropriate partial safety factors for these loads. 2. ESTIMATE ALLOWABLE BEARING PRESSURE OF SOIL USING GROUND INVESTIGATION REPORT. From a study of the site ground investigation (if available), the strength of

Shear cap vs drop panel

 Shear cap vs drop panel  Flat slab design is usually associated with punching shear. In order to reduce the shear stress induced around columns designers usually increase the slab thickness near the column. This increase in thickness in the vicinity of columns is usually called " drop panel ".  Is it technically correct to call every thickness increase around columns drop panel? The answer to this question is NO! And let's see an article from ACI 318-14 to arrive at a correct naming/term. drop panel -  projection below the slab  used to reduce the amount of negative reinforcement over a column or the minimum required slab thickness, and to increase the slab shear strength. shear cap - projection below the slab used to increase the slab shear strength shear caps (popularly called  shear  heads) are commonly used, especially when the transverse reinforcement does not give the required load capacity. The second advantage of using the shear heads is the increased stiffnes

What is The Difference Between Expressway, Highway, Motorway, Causeway, And Freeway

  The Difference Between Expressway, Highway,  Motorway, Causeway, And Freeway        Various road terminologies are bound to be used without proper or thorough information or enlightenment on the reasons behind such terminologies. Roads come in different types and for different utilization.  1. Expressway. An expressway is a wide road which is targeted at fast moving traffic. Unlike many other roads on the list, the expressway features multiple demarcated lanes which could also include a service lane. The point of the expressway is to promote smooth movement of traffic by dedicating lanes for vehicles about to use the intersections. As earlier stated, most expressways include a service lane. This auxiliary lane is meant for vehicles about to access a street or an intersection. The purpose of the service lane is so that these cars do not disturb the rest of the cars navigating the major roads on the expressway.   2. Highway. Highway is a term used to describe a stretch of road connecti